Objective: To construct a state-of-the-art data center that meets the organization’s storage, processing, and networking needs.
Start Date: [Insert Start Date]
Task Breakdown
Task#
Task
Depends on
Duration
Start Date
End Date
Assignee
Notes
1
Define project requirements
2
Secure project funding
3
Select a suitable location
2
4
Obtain necessary permits
3
5
Design data center layout
3
6
Choose technology and equipment
5
7
Develop project budget
5, 6
8
Hire contractors and vendors
5, 6
9
Create project timeline
7
10
Prepare site
8
11
Begin construction
10
12
Install power and cooling systems
11
13
Install networking infrastructure
12
14
Set up servers and storage systems
12, 13
15
Conduct system integration
14
16
Perform initial testing
15
17
Address any issues found in testing
16
18
Conduct final testing and validation
17
19
Train staff on new systems
18
20
Launch data center
19
21
Monitor and maintain operations
20
Project Team and Responsibilities
Team Member
Role
Responsibilities
Person(s)
Project Manager
Oversees project progress
Manages resources and ensures timely completion
Architect
Designs data center layout
Creates detailed design plans for the facility
IT Specialist
Selects technology and equipment
Ensures compatibility and future-proofing
Construction Manager
Supervises construction
Oversees site preparation and building process
Network Engineer
Installs networking systems
Sets up network infrastructure and connectivity
Power/Cooling Specialist
Installs power and cooling systems
Ensures efficient and reliable operations
QA Tester
Tests systems
Conducts testing and validation of data center systems
Training Coordinator
Trains staff
Provides training on new systems and procedures
Risk and Risk Management
Risk
Impact
Probability
Mitigation Strategy
Person(s)
Delays in Construction
High
Medium
Create a detailed timeline and monitor progress
Budget Overruns
High
Medium
Maintain a contingency fund and track expenses closely
Technology Compatibility Issues
Medium
Low
Conduct thorough research and testing before purchasing
Permit Delays
Medium
Medium
Start permit application process early
Power/Cooling Failures
High
Low
Regularly maintain and test power and cooling systems
Security Breaches
High
Low
Implement robust security measures and regular audits
Communications Plan
Communication Type
Frequency
Participants
Purpose
Planning Meetings
Weekly
Project Team
Discuss project progress and address issues
Budget Reviews
Bi-weekly
Budget Manager, Project Manager
Track and review project expenses
Construction Updates
Daily during construction
Construction Manager, Project Manager
Review daily progress and plan for the day
Technical Coordination
As needed
IT Specialist, Network Engineer
Ensure compatibility and integration of systems
Final Review Meeting
One-time
All stakeholders
Conduct final project assessment and review
Success Criteria
Metric
Target
Target Amount
Project Completion
Finish on or before scheduled date
Budget Adherence
Stay within planned budget
System Performance
Meet or exceed performance benchmarks
Security
No security breaches within the first year of operation
Customer Satisfaction
High satisfaction rating from internal and external users
Budget
Item
Description
Amount
Construction Costs
Expenses for building the facility
Power Systems
Cost of power supply and backup systems
Cooling Systems
Cost of cooling infrastructure
Networking Equipment
Expenses for network setup
Servers and Storage
Cost of servers and storage systems
Permits
Fees for obtaining necessary permits
Labor
Wages for contractors and staff
Miscellaneous
Any other unforeseen expenses
Total